Section
2(1)(h) and 34 (3) - Meaning of delivery of award
by the Tribunal to the 'party'
2005(1)
RAJ 506 (SC)
Union of India Vs Tecco Trichy Engineers & Contractors
Decided on 16.3.2005
The
Southern Railway entered into a contract with the
Respondent and the contract was signed by the then
Chief Project Manager, presently the Chief Engineer
(CE). When disputes arose, in exercise of the power
conferred by the arbitration clause in the contract,
the General Manager (GM), Southern Railway, appointed
an arbitrator as well as the presiding arbitrator.
The tribunal so constituted gave its award, a copy
of which was delivered on 12.3.2001 in the GM's office
and receipt of the same was acknowledged by someone
in the office. The CE received the award copy on 19.3.2001.
On 10.7.2001,
the CE applied for setting aside the award and an
application for condonation of delay of 27 days was
filed under S.34(3), based on the assumption that
the award was received on 19.3.2001. The Respondent
contested this application saying that the award was
delivered on 12.3.2001 and the High Court agreed with
the Respondent.
It was
held that according to Section 31(5), 'after the arbitral
award is made, a signed copy shall be delivered to
each party'. Section 2(1)(h) defines a "party"
as meaning 'a party to an arbitration agreement'.
The court examined the meaning assigned to the term
"party" in the context of the State or a
Government Department, esp. a large organization like
the Railways.
It is
well known that the Ministry of Railways has a very
large area of operation covering several divisions
with different division heads and departments with
their own department heads. The GM, at the apex position,
holds responsibility for strategic decisions, organizational
policies, administrative instructions etc. The day
to day management and operations of different departments
rest with different department heads, who are directly
connection with their department's functioning and
is alone expected to know the progress of the matter
pending before the arbitral tribunal.
Thus,
in a large organization like the Railways, "party"
as referred to in Section 2(1)(h) r/w Section 34(3)
has to be construed to be a person directly connected
and involved in the proceedings and who is in control
of the proceedings before the arbitrator.
The
delivery of an arbitral award, to be effective, has
to be 'received' by the party and this delivery by
the tribunal and receipt by the party sets in motion
several periods of limitation, therefore it is an
important stage in the arbitral proceedings.
The
court held that in the present case, the CE had signed
the agreement on behalf of the Railways. In the arbitral
proceedings, he represented the organization and notices
were served on him. Even the award clearly mentioned
that the Railways is represented by DY. CE/Gauge Conversion,
Chennai. The subject matter of arbitration related
to the department of the CE. Therefore, the High Court
had erred in its decision and the Claimant's application
for setting aside the award is allowed.
Section
2(2) & 9 - Mainatinability
1999(1)
RAJ 385 (Del)
Kitechnology NV Vs Unicor GMBH Plastmaschinen
Both
the parties to the agreement were foreigners and the
agreement specifically agreed that the agreement was
to be governed by German laws, the dispute was to
be resolved by arbitration and the seat of arbitration
was to be at Frankfurt.
It was
held that this Act applies in cases where one or more
parties is a foreigner but the place of arbitration
is India. According to the arbitration agreement of
the parties, the German court has exclusive and competent
jurisdiction with respect to the dispute.
It follows
that where the parties to the agreement were foreigners
and the place of arbitration was not in India and
a foreign law was applicable, then provisions of Part
I of this Act are not applicable. In view of Section
2(2), this is not international commercial arbitration
to which Part I will apply. Therefore an application
under Section 9 is not maintainable.
Section
8(2) - Xerox copy of original arbitration agreement
is acceptable
1998(2)
RAJ 141 (Cal)
ITC Classic Finance Ltd Vs. Grapco Mining & Co
The
issue came up as the present application had annexed
with it, Xerox copies of the lease agreement which
also formed part of the plaint filed in the suit.
The said lease agreements were relied upon by both
the parties and it was not disputed that the said
Xerox copies were indeed true copies of the original
documents. It was held that the Xerox copies of the
said lease agreement containing the arbitration clause
were in sufficient compliance with Section 8(2) of
the Act.
Section
8(3) - Reference of dispute to arbitrator during pendency
of civil suit
2000(3)
RAJ 511 (P&H)
Punjab State Cooperative Supply and Marketing Federation
Ltd Vs. Shiv Rice and General Mills
The
question that arose before the court was about the
permissibility of reference of disputes to an arbitrator
during the pendency of a suit in the Civil Court.
It was
held that the courts cannot restrain the arbitrator
from proceeding in arbitration or restrain the defendants
from proceeding with arbitration before the arbitrator.
The
plea regarding jurisdiction of the arbitrator could
be raised before the arbitrator and if the arbitrator
did not agree to the plea and an award was passed
against the plaintiff, then the plaintiff was competent
to challenge the same u/s 34 of the 1996 Act and the
Court was competent to set aside the award if it dealt
with a dispute not contemplated by or not falling
within the terms of the arbitration clause.
Section
8(3) contemplates a situation where the matter may
be pending before the Court and still the arbitration
may be commenced or continued and an arbitral award
made. The aggrieved party may challenge the award
u/s 34 of the 1996 Act.
Section
9 & 17 - Life of an Interim Order
2005
(1) RAJ 225 (Raj)
Air Conditioning Corporation Ltd, Calcutta Vs. Rajasthan
Agriculture University, Bikaner
According
to the facts, a dispute arose between the parties
which was referred to arbitration in 1999. While the
proceedings were going on, the petitioner filed an
application u/s 17 for interim measures which was
allowed by the arbitrator in 2002. The Respondent
appealed before the District Judge Bikaner u/s 37
and the order was set aside. Aggrieved by this decision,
the petitioner filed the revision petition which was
allowed.
The
petitioner, in 2004, had filed another application
u/s 151 CPC stating that since the arbitrator had
passed the final award in 2003, which was published
in 2004, the respondent should be directed to pay
according to the terms of the award.
It was
held that there is no dispute that if any final order
is passed in the proceedings before any forum, the
life of the interim order comes to an end with the
passing of the final order in that proceeding. In
the present case, the arbitrator had passed an interim
award in 2002, which was set aside by the District
Judge. However, with the passing of the award in 2003,
the life of the interim order dt. 2002 passed away
and therefore, this revision petition has become infructuous.
It was
further held that this Court cannot given any directions
for execution of terms of the final award because
it will be the domain of the Executing Court before
whom the execution petition for executing the award
is filed.
AIR
1999 (SC) 565
Sundaram Finance Ltd Vs NEPC India Ltd
This
case discussed the similarity between Section 9 of
the 1996 Act and Article 9 of UNCITRAL Model Law which
states that "It is not incompatible with an arbitration
agreement for a party to request, before or during
arbitral proceedings, from a court an interim measure
of protection and for a court to grant such measure"
Article
9 seeks to clarify that merely because a party to
an arbitration agreement requests the court for an
interim measure "before or during arbitration
proceedings", such recourse would not be regarded
as being incompatible with an arbitration agreement.
Arbitration may commence and continue notwithstanding
a party having approached the court for interim protection.
The
expression "before or during arbitration proceedings"
used in Section 9 seems to have been inserted with
a view to give it the same meaning as those words
in Article 9 of UNCITRAL Model Law.
Section
9 & 45 - Application u/s 9 does not constitute
waiver or abandonment of arbitration clause
2001(3)
RAJ 433 (Del)
Bharti Televentures Ltd Vs DSS Enterprises
In the
instant case, DSS filed an injunction suit restraining
CGL from selling or transferring its shares in Skycell.
It was
held that although the provisions of Section 9 cannot
be resorted to for interim measures where the parties
have chosen a foreign forum for arbitration, the fact
remains that such a step cannot constitute a waiver
or abandonment of the arbitration clause.
In Sundaram
Finance Ltd Vs NEPC Ltd [1999(1) RAJ 365], it has
been held that when a party applies u/s 9, it is implicit
that it accepts that there is a final and binding
arbitration agreement in existence. When such an application
is filled before the commencement of arbitration proceedings,
there has to be manifest intention on the part of
the applicant to take recourse to arbitral proceedings.
Thus, the mere filing of application u/s 9 by any
of the parties does not operate waiver or estoppel
from invoking the arbitral proceedings.
Similarly,
the suit filed by DSS does not operate as a waiver
as it was a suit for injunction restraining CGL from
transferring or selling its shares in Skycell and
was not covered by Section 62 of the Indian Contract
Act not was it a suit with regard to the provisions
of the Joint Venture Agreement. It relates to the
Articles of Association of the company.
Section
9, 2(1)(e), 42 - Determination of proper court for
application u/s 9
2003(4)
RAJ 661 (All)
Payal Enterprises Vs Union Of India
An application
u/s 11 for appointment of arbitrator was pending before
the Chief Justice. The question that arose was whether
application u/s 9 was to be filed before the Chief
Justice in view of Section 42 of the Act.
Held,
it is true that Section 42, which defines jurisdiction,
says that where with respect to an arbitration agreement,
any application under this part has been made in a
court, that court alone shall have jurisdiction over
the arbitral proceedings and all subsequent applications
arising out of that agreement and the arbitral proceedings
shall be made in that court only. The word 'court'
as defined in Section 2 (1)(e) means the principal
civil court of original jurisdiction or the High Court
exercising original civil jurisdiction.
It is
settled view that the Chief Justice acting u/s 11
of the Act does not act judicially and therefore is
not a court as defined in Section 2(1)(e). Therefore
the application u/s 9 is not maintainable before the
Chief Justice and it will lie before the Court as
defined in Section 2(1)(e)., ie. The principal civil
court of original jurisdiction ie. The District Judge
Section
9, 48(3) - Interim injunction during pendency of proceedings
in foreign country
2000(4)
RAJ 512 (Del)
Naval Gent Maritime Ltd Vs Shivnath Rai Harnarain
According
to the facts, the Respondent is an Indian company
whose assets are entirely located in India. The proceedings
were initiated in England. The issue was whether interim
injunction could be granted in India.
It was
held that so long as the territorial jurisdiction
of the court is present, relief should not be declined
on technicalities which are not representative of
any equities in favour of the Respondents. Since the
Respondent's properties are located in India, the
umbilical cord of territoriality is clearly visible.
In the
case 'The Channel Tunnel Group Vs Balfour Beatty Construction
Ltd & Ors [1993(1) All ER 64], it was held that
the English courts possessed inherent powers to grant
interim relief even where the seat of arbitration
was not in England. This view has now obtained statutory
sanction in terms of the English Arbitration Act.
This is the ubiquitous view internationally. There
is no reason to adopt a pedantic approach, thereby
rendering the legal regime in India dissimilar to
that prevailing in other parts of the world.
The
globe is now becoming a village and persons will have
increasing power to choose between several available
courts, so long as the choice is not capricious, relief
should not be denied.
Section
9, 2(2), 17 - No order permissible by court where
arbitration held outside India
2001(1)
RAJ 93 (Del)
Marriott International Inc Vs Ansal Hotels Ltd
The
parties had agreed to have their disputes referred
to the arbitration of the Kuala Lumpur Regional Centre
for Arbitration (KLRCA) in accordance with their rules.
Under Rule 1, the disputes were to be settled in accordance
with the UNCITRAL Arbitration rules subject to modification
as set forth in the KLRCA Rules. However, the KLRCA
Rules made a departure from the UNCITRAL Model Laws
and had made no provisions like our Article 9 in Part
II of the Act.
The
counsel for one of the parties argued that in case
the provisions of the India Act did not apply, the
Court had inherent powers u/s 151 CPC to pass an interim
order.
The
Court agreeing on otherwise, held that in case this
Court, in view of S.2(2), does not have any jurisdiction
to pass an interim order contemplated by S.9, then
the Court cannot exercise inherent powers and thereby
confer upon itself a jurisdiction not conferred by
law. To exercise any inherent power, the Court must
have jurisdiction over the proceedings over it.
However,
a party is not left remedyless n as much as it can
approach the Arbitral Tribunal for passing appropriate
orders to take interim measures as it may deem necessary
in respect of the subject matter of the dispute. The
Tribunal may pass such interim measure in the form
of an interim award, which may be enforced as an arbitral
award.
Section
9 & 34 - Interim measures independent of any substantive
proceedings
2000(2)
RAJ 112 (All)
Deepak Mitra Vs District Judge, Allahbad
The
permissibility of application for interim measures,
independent of substantive proceedings was discussed
in this case. This Court chose to disagree with another
recent decision of Delhi High Court [Ashok Chawla
Vs Rakesh Gupta: 1996(37) DRJ 566] which had taken
the view that a petition u/s 9 is not entertainable
except in the course of proceedings for substantive
relief under the Act.
This
Court, on the other hand, held that the letter and
spirit of Section 9 indicate that it is a self contained
provision contemplating that a party may make independent
and substantive application under this provision.
The party need not have made an application for substantive
relief in relation to arbitration matters and in such
proceedings, only should have made an application
for interim relief u/s 9.
It was
further held that the only source of powers of the
Court to make orders by way of interim measures is
Section 9 and there is not independent power dehors
that provision. The Court is aware that the case law
on this point is exiguous which may, however, grow
only with the passage of time but the interpretation
that the Court may make interim measures independent
of any substantive proceedings appears to be consistent
with the changes brought about by the 1996 Act.
Section
9 - Remedy not available if arbitrator has jurisdiction
in the matter
2002(1)
RAJ 285 (Del)
Arun Kapoor Vs Vikram Kapoor
According
to the facts, the parties had referred their dispute
to a sole arbitrator and terms of settlement of interim
arrangement was reached before the Tribunal. The petitioner
had moved twice before the arbitrator to obtain injunction
and had failed in the attempt. Thereafter, he filed
an application for an identical injunction in this
court, during the pendency of arbitral proceedings.
It was
held that it is a cardinal rule that if the party
invokes preliminary alternative remedy before the
Arbitral Tribunal, it is debarred from invoking the
jurisdiction of the Court u/s 9. Ordinarily, if the
arbitrator is seized of the matter the interim relief
should not be entertained and the parties should be
advised to approach the arbitrator unless and until
the nature of relief intended to be sought falls outside
the jurisdiction of the arbitrator or beyond the terms
of the agreement or reference of disputes. Otherwise
the very object of adjudication of disputes by arbitration
would stand frustrated. A party should be discouraged
to knock on the door of the Court, particularly when
the arbitrator is seized of all the relevant or even
ancillary disputes.
Section
9(ii)(e) - Impermissibility of challenge to appointment
and venue after giving consent
2002(1)
RAJ 40 (Mad)
Kamala Solvent Vs Manipal Finance Corporation Ltd,
Manipal
The
applicant herein had invoked the provisions of Section
9 (ii)(e) and had filed the present application seeking
an injunction restraining the 3rd respondent (who
is the sole arbitrator) from proceeding further with
the proposed arbitration.
It was
held that such an application is unsustainable since
under the agreement, the applicant had admittedly
given consent for the appointment of the 3rd respondent
as sole arbitrator and also for the venue of the arbitration
proceedings. This being the case, it is not open for
the applicant now to challenge the appointment of
the arbitrator.
Section
9 - petition u/s9 not maintainable without substantive
move for reference
1998(1)
RAJ 540 (Del)
National Building Construction Corpn Ltd (NBCC) Vs
IRCON International Ltd.
The
petitioner had moved the court u/s 9 for interim relief,
however, the matter was neither referred to arbitration
not was anything done to move for reference.
It was
held that Section 9 provides that a party may, before
or during arbitral proceedings or at any time after
making of the arbitral award but before it is enforced
in accordance with Section 36, may apply to the court
for interim injunction. In this case, the matter has
neither been referred to arbitration nor has anything
been done so far to move for reference. Since no steps
for substantive relief on it had been taken, the petitioner's
application was dismissed.
Section
9 - petition u/s9 without referring dispute to arbitrators
maintainable
2003(2)
RAJ 582 (Mad)
Hairtha Finance Ltd Vs ATV Projects India Ltd
The
applicant had filed an application u/s 9(ii) for interim
protection and the Counsel for the respondent objected
that since there is a dispute regarding appointment
of the arbitrator, which itself pending, the applicant
cannot sustain the application filed u/s 9 (ii) (a),
(b), (c) or (e).
It was
held that such a submission cannot be countenanced.
Section 9 can be invoked even without referring the
dispute to the arbitrators as the requirement is that
there should be a dispute which is referable to the
arbitral tribunal. It was not disputed that such a
requirement was in existence in this case.
Section
9 & 17 - Scope of power of the court
2003(2)
RAJ 163 (Bom)
Maharashtra State Electricity Board Vs Datar Switchgear
Ltd
This
case discussed the scope of power of the court u/s
9 vis a vis the powers granted to the arbitrator u/s
17. The court held that if the power that has been
conferred upon the court u/s9 is compared with the
power conferred on the arbitral tribunal u/s17, it
is immediately noticeable that the court can exercise
its power either before or during arbitral proceedings
or even thereafter upon making of the award but before
it is enforced. The Act does not contemplate interference
of courts at the interim stage in matters of jurisdiction
of the Tribunal or n challenges to the existence or
validity of the arbitration agreement.
u/s
9(ii)(e), the court is conferred with residuary power
which is sufficiently wide to provide an avenue of
redressal to ensure and protect a party against abuse
of the arbitral process and grant such interim protection
as it may appear to the court to be just and fair.
Unlike the power of the arbitral tribunal u/s17, which
is co-extensive with the continuation of arbitral
proceedings, the power of the court u/s 9 arises both
before and during arbitral proceedings and even thereafter.
The court must be bound by the general discipline
of the Act, which constitutes a code in itself, that
discipline being of limited judicial intervention.
Therefore, in consonance with the norm of restricted
judicial intervention, the court has to assess whether
a strong prima facie case has been made out for the
exercise of its jurisdiction u/s 9(ii)(e).
A prayer
for relief u/s 9(ii)(e) is not a substitute for enforcing
the order of the tribunal. A willful disregard of
the tribunal's order must be shown to exist. The court
has to exercise its powers u/s 9 with caution and
circumspection. A default in effecting payment cannot
be a ground in itself to justify exercise of power
by the court u/s 9.
Section
9 - whether proceedings u/s 9 barred by provisions
of 22(1) and 32(1) of SICA
2003(3)
RAJ 554 (Mad)
Sivananda Steels Ltd Vs India Cements Capital Finance
Ltd
There
was a hire-purchase agreement b/w the parties in respect
of machineries. The appellant company was declared
sick u/s 3(1)(o) of SICA Act. An arbitrator was appointed
to adjudicate the claim. When the appellant committed
a default, the respondent invoked section 9 of the
Act, as the machineries in question were owned by
the respondent. The question that arose was whether
proceedings u/s 9 were barred by Section 22(1) and
32(1) of SICA.
It was
held that the action initiated by the respondent u/s
9 of the Act was not inconsistent to the SICA Act,
Rules or Schemes, both on the score of general overriding
provisions in Section 32(1) as also the specific overriding
provisions in sub sections 16(5), 22(1), 22(2),22(3),
22(4) and 23(1). Nothing is indicated that they prevail
over the Arbitration Act, ie. Section 32(1) has overriding
effect only in respect of those laws which are inconsistent
with the said Act on the same subject. The Arbitration
Act and SICA Act occupy 2 separate and distinct fields,
hence there arises no question of repugnancy between
the two.
Here,
allowing the appellant company to continue in possession
of the machineries belonging to the respondent would
cause further liability for the respondent who would
continue to suffer loss till the disposal of the case
by BIFR or AIFR. Section 22 of SICA was not enacted
to aggravate the financial difficulties of a sick
company. Therefore sections 22(1) and 32(1) do not
bar proceedings u/s 9 of the Arbitration Act.
more....